October 2002

Barnhart, Inc. completes design-build BEQ

Contractor built facility at MGAGCC Twentynine Palms

Barnhart, Inc. completed a $14 million design-build, Bachelors Enlisted Quarters (BEQ) at the Marine Corps Air Ground Combat Center (MCAGCC) in Twentynine Palms, CA.

With design partner Delawie Wilkes Rodrigues Barker, Barnhart oversaw the design and construction of the 87,855-sf BEQ. The three-story masonry building features slab on grade, steel framing, metal decking on upper floors with concrete topping and metal roofing.

The project began construction August 6, 2001 and was completed in September 2002. The facility houses 384 personnel attending the Marine Corps Communications Electronics School.

Barnhart has successfully teamed with Delawie Wilkes Rodrigues Barker on past BEQ projects, including recent renovations to BEQ's at the Naval Station San Diego.