| August
2003
Ran:
Valley Chronicle - August 2003
Hemet
High's renovation nears completion on time
By:
Gail MacMillan
With
the start of classes just nine days away, Hemet High is still
more job site than school site as workers labor down to the
wire to finish the most extensive modernization project in
school district history.
Stacks
of sheet rock and long bolts of carpeting fill the quad. Painters
cover walls in bright gold and red. Plumbers install new bathroom
fixtures over bright white tile and upstairs, thousands of
feet of new duct work is being sealed off as soon as communication
cables are pulled through.
The work
is the completion of a $7.73 million modernization project
to bring the 30-year-old high school into the 21st century.
Work was funded by local Measure E bonds approved by taxpayers
last year and by statewide ballot initiative Proposition 47
approved this spring.
Taxpayer
blessing meant seeming chaos at the high school this summer.
With just 72 days to complete the job, workers gutted and
rebuilt the main building as they installed several thousand
feet of duct work for air conditioning, new T-Bar in the ceiling,
new flooring and new paint. Walls have been made fire safe,
some corridors and half walls have been capped off to meet
fire regulations. Science classrooms and some exterior walls
sport additional doors and new doors were installed elsewhere.
And since
much of the main campus building had to be gutted, workers
now must replace all cabling and wiring to bring the building
back into working order. Five sprinkler heights had to be
adjusted and the school cafeteria was brought up to current
code. New serving windows were cut into an outside wall to
provide a second point of service during the lunch rush.
Through
it all, workers have labored through 14-hour days and double
shifts without air conditioning. Testing on the revamped air
chiller started Wednesday.
"It's
pretty warm all right," admits construction superintendent
Bill Downing, with contractor Douglas E. Barnhart.
But air
is a minor concern compared to other challenges faced this
summer.
Only
three weeks before demolition, original project superintendent
Dave Dever was killed in a head-on collision en route to Hemet
from his Orange County home. Dever had been planning the modernization
project with district staff since its inception and the loss
was devastating to staff both personally and professionally.
"It's
been beyond unbelievable this summer," said Sandy Packham,
director of facilities for Hemet Unified, who is overseeing
modernization projects at several campuses this summer. Besides
the high school, she is in charge of building two new elementary
campuses and several smaller modernization projects at different
schools. "We knew it would be down to the wire."
Administration
staff was due to return to newly revamped offices Friday.
Teachers will return Monday. Packham is bringing in a crew
of professional cleaners to remove the fine concrete silt
and to spiffy up classrooms to make them ready for furniture.
In the quad, hundreds of classroom door windows are sprayed
red in preparation for installation.
Modernization
of a 30-year-old campus is filled with unexpected challenges.
The original elevator shaft is eight inches smaller than called
for in original plans. The shaft was concreted off after the
school was built before an elevator was installed. A new elevator
is now delayed, but should be installed by October.
New windows
replace those that suffered gaps when the building settled
after its construction in the early 1970s. Rearrangements
over the decades led to corridors that incorrectly appeared
to lead outdoors - which could be tragic in case of fire.
Now, Packham says, "if it looks like a corridor, it really
is."
The entire
career center had to be rebuilt since none of the original
construction net current code.
To meet
fire codes, the once-open library is now closed off from the
upper corridors.
Science
classrooms now have two exits since rooms exceed 1,000 square
feet. Staff restrooms were reconfigured to provide more room
and handicap accessibility. Student restrooms have no tile
and fixtures.
"It's
the largest restoration we've ever done," Packham said.
"It's amazing what has been done this summer."
Demolition
started at noon on Friday, June 13. Packham said teams of
workers and equipment were waiting for the final student to
leave campus before they moved in and started knocking down
walls.
Proposed
high school may find home in Hemet
Hemet's
newest high school may be in Hemet after all.
Trustees
will vote Tuesday whether to approve examination of a new
property within Hemet city limits for the city's third high
school scheduled to be build within the next few years.
Superintendent
Phil Pendley said staff is considering a 112-acre site near
the confluence of Fruitvale, Cawston and Commonwealth. Pendley
brought the site before Hemet City Council last week.
The site
is nearly twice as large as a previously considered site near
Sanderson and Esplanade avenues in San Jacinto. Board members
expressed concern about build a Hemet Unified high school
outside city limits. Pendley cautioned that examining the
new property does not mean that staff will be closing the
door on the San Jacinto property, which is within Hemet Unified's
boundaries.
The new
Hemet site is further west than previously considered sites
and once served as a dairy. While there would be issues with
site clean up, "it's nothing insurmountable that we can
see now," Pendley said.
The site
will be discussed at 6:30 p.m. Tuesday at Hemet Unified's
board meeting at the district office, 2350 West Latham Avenue
in Hemet.
Back
|