| August
2003
Ran:
San Diego Union-Tribune North Inland - Friday,
August 15, 2003
Despite
Bees, swarm of workers busy on 3 Fallbrook schools
By:
Patty McCormac
FALLBROOK
- The mission: to complete a $15 million modernization project
at three schools, all during 72 days of summer vacation.
Status
report: Despite encounters with bees and asbestos, everything
should be ready by Aug. 25, the first day of school.
"We're
on schedule," said David Medcalf, vice president of Douglas
E. Barnhart Inc., the contractor. "We will probably be
working the evening before school opens, but that is not usual."
Before
construction began, Barnhart and the Fallbrook Chamber of
Commerce distributed a request for "mega contractors"
capable of a two-shift operation. Barnhart, which has offices
in Palm Springs, Sacramento and San Diego, got the nod.
"There
was a large scope of work they have to do in this type of
job, in that time frame," Medcalf said. "Certain
contractors have the ability."
Seven
days a week this summer, an average of 325 workers have been
swarming over Mary Fay Pendleton School on Camp Pendleton,
Fallbrook Street School and Potter Junior High School, gutting
classrooms, digging trenches and installing new plumbing,
storm drains, sewer systems, electric lines and concrete walkways.
"Since
the job started we have been working every day," Medcalf
said. "All of the trades will be accelerated now. Some
of the crews that were working 12 hours a day have gone back
to eight, while some, like the finish trades, who were working
eight are not working 12."
An intense
four months of planning before construction started has helped
iron out most-but not all-kinks.
Materials
were purchased and the construction schedule finalized in
advance, so that workers were poised to begin the minute school
got out in June.
"The
analogy that has been floating around is that it was like
a Mervyn's sale where everyone kind of rushes in," Medcalf
said.
The improvements
are the first using money from a $32 million bond measure
approved by Fallbrook voters in November 2002. Next summer
three more schools will be remodeled.
Though
this summer's work appears on track and under budges, there
were a number of surprises. But there were bound to be when
tearing open schools built from 1938 to the 1960s, said Ray
Proctor, assistant superintendent of the Fallbrook Elementary
School District.
Workers
found bees in the walls of Mary Fay Pendleton school.
"It
was a hive in there," Proctor said. "They had to
pull it out and resheet that. There was also asbestos in the
plaster of the multipurpose room there and in some ceiling
tiles at Potter."
"It's
not unusual to find asbestos in an old building, but bees
are," Medcalf said. "We had to take the siding off
and remove the bees."
There
also was the matter of using explosives on Camp Pendleton
to remove granite to make way for storm drains and sewers
at Mary Fay.
Work
crews got a permit to bring the explosives on base, but for
a time there was question about actually being permitted to
use them due to security concerns.
"We
just had some procedural issues that needed to be taking care
of," Medcalf said. "It didn't impact our schedule
for more than one day. The base wanted to have a few forms
filled out that identified what material we were using."
Another
setback was having to rip up about $250,000 worth of concrete
walkway to satisfy requirements of the Americans With Disabilities
Act. That's because a half-inch difference in height between
a walkway and a doorway was once considered acceptable, but
is no longer allowed.
What
was supposed to be a fairly easy modernization of the Bowers
Auditorium on the grounds of Potter Junior High quickly grew
more complicated.
Plans
had called for fixing a leaky roof and adding wheelchair lifts,
wheelchair ramps, new flooring, lighting and an air-conditioning
system.
Once
workers got inside the 10,000-square-foot auditorium, built
in the 1960s, they found structural issues in the ceiling
and roof that made a new roof necessary. The cost will be
about $1.4 million, Proctor said, and should be finished by
December.
Even
with all the surprises, the project is about $350,000 under
budget, Proctor said. New heating and air-conditioning systems
have been installed in classrooms, along with computer-friendly
wiring, dropped ceilings, new sinks, cabinets and walls.
"I
am very pleased with what has been happening," said Wil
Gower, chairman of an oversight committee which keeps tabs
on the project. The committee will report back to the community
in the fall.
Back
|