|
August
2003
Ran:
Fallbrook/Bonsall Village News - Thursday,
August 21, 2003
Countdown
to the classroom
By:
Debbie Ramsey
Community
members, parents and students have watched in shock and wonder
as three local elementary school campuses have been massively
disassembled over 70 days of the summer vacation for a total
of $19.5 million in badly needed renovations - the first expenditure
from the November 2002 $32 million bond measure.
The question
in the minds of many remains "Will they finish in time
for school to start?" With FIESD classes scheduled to
resume on Wednesday, August 27, Business Manager Ray Proctor
remains confident that the contractor, Douglas E. Barnhart
Inc. will indeed meet the deadline.
"Everything
is going to be ready for school on Wednesday," Proctor
stated. "I am confident that Barnhart will have them
done, even if it means working until midnight the night before.
They have done a great job and I am very pleased with their
team." The team numbers over 300 construction workers
on the job each day between the three sites. Proctor is also
pleased that the three projects (Fallbrook Street, Potter
Junior High and Mary Fay Pendleton) have come in over $380,000
under the combined updated (6-1-03) budget.
"We
are bringing in extra custodians to the sites on Monday and
Tuesday to help get things cleaned up and help the teachers
move into their classrooms," Proctor said. "I expect
to have nice, clean classrooms. They might not have everything
up on the walls, but they will have a great learning environment."
While
the schools are expected to be functional, don't expect to
see lavish landscape in place where extensive ground excavation
has occurred. With only $100,000 allocated in the budget collectively
for the replanting of landscape at all three schools, Proctor
says the decision will be up to the Board of Trustees to determine
how much landscape will be replaced and how soon.
"There
is no way we could have the construction and full landscaping
done in 70 days," Proctor explained. "With the $100,000
we will start to hook up sprinklers and see how far we can
go. After that we will have to use our District funds and
staff to phase in landscape and planter beds during the rest
of the school year."
One of
the most visible construction sites this summer has been Potter
Junior High School, originally built in 1964. On the heavily
traveled Reche Road, the renovation project budgeted at $6.2
million has been observed by many motorists. Summer improvements
include expanding restrooms, replacing plumbing and sewer
systems, upgrading electrical systems, and making numerous
other health and safety improvements. In addition, they have
constructed and upgraded heating and air conditioning systems,
modernized classrooms and constructed student support facilities,
constructed and renovated science classrooms, and constructed
new classrooms and locker rooms. The school site has also
been wired for computer access. To date, this project site
is over budget by $1.6 million due to additional asbestos
abatement that was needed, termite damage and wood replacement,
DSA rules on concrete for ADA requirements and underground
granite demolition and removal. Potter's auditorium needed
more attention than first tests showed due to dry rot damage.
At Fallbrook
Street School, a budget of $7.2 million allowed for more of
the same type of improvements for the campus built in 1953.
Restrooms were expanded and plumbing and sewer systems were
replaced. Electrical systems were upgraded and classrooms
were modernized. It was necessary to construct and upgrade
heating and air conditioning systems and improve the play
court and parking surfaces. This school was also wired for
computer access. To date, cost has been $5.2 million - making
this project under budget by $2 million. The only unexpected
item that cropped up on this campus was the need to remove
a bee's nest.
May Fay
Pendleton School was set to receive $6.3 million in improvements
for the campus built in 1954 and has come in fairly close
at $30,000 under budget. Health and safety improvements paralleled
the other schools with expansion of restrooms and the replacement
of plumbing, sewer, electrical, air conditioning, and heating
systems. The parking area and traffic circulation was addressed
as well. Bees posed a larger problem at Mary Fay Pendleton,
however. The bees were discovered inside the siding of one
of the buildings, requiring the siding to be removed, the
bees relocated, and honey removed.
Proctor
admits the projects this summer have been massive and credits
the advance testing done at the sites for keeping the work
within budget.
"The
norm for a project like this would be to allow for 10 - 15%
in change orders," Proctor said. "Because of the
advance testing, we allowed for 5% for the unforeseen. We
think that is what really saved us. It helped us learn more,
in depth, about the condition of our campuses."
While
Proctor sees the light at the end of this particular tunnel,
he is already lining up another - next summer's renovation
projects.
"Next
summer we will go through the same renovation process with
Maie Ellis (built in 1938), La Paloma (built in 1968) and
San Onofre (built in 1974)," he said. "The architects
are working right now on those plans."
"This
is the largest-scale renovation these campuses have ever seen,"
Proctor said. "There's been nothing like this to date.
It has made me in awe of how they can rip things up and put
them back together so quickly."
Back
|